From an Idea to a Working Elephant Water Pond
The Project

From an Idea to a Working Elephant Water Pond

A three-month pilot, led by youth and owned by the community — from first consultation to a monitored, working water pond.

Project overview

Metsi a Ditlou at a glance

Project
Community-Managed Water Ponds for Elephants
Project Lead
Happy Puseletso Mbambo
Location
Kauxwi/Kauwxi, Okavango East, North-West District, Botswana
Duration
3 Months
Proposed Start
10 November 2026
Project objectives

Four goals for the pilot

01

Construct the pond

Construct one solar-powered water pond along an identified elephant corridor.

02

Train Pond Guardians

Train 10 young people as Pond Guardians to monitor the pond and collect data.

03

Engage the village

Engage one village in planning, construction and maintenance.

04

Educate the community

Educate 200 community members and students about human-elephant coexistence.

How the project will happen

Eight phases, one working pond

The pilot runs across the three-month period, from first consultation through to monitoring and reporting.

Phase 1

Community Consultation

Meet community members, elders and relevant stakeholders to discuss the proposed location and identify the most appropriate site.

Phase 2

Site Mapping

Work with local leadership and the Department of Wildlife and National Parks (DWNP) to map and confirm the site.

Phase 3

Construction

Procure materials and begin construction of the pilot water pond.

Phase 4

Solar Installation

Install the solar-powered water system, including pump, tank and pipes.

Phase 5

Pond Guardian Training

Train 10 young people as Pond Guardians to help monitor the pond and collect information.

Phase 6

Wildlife Monitoring

Install a camera trap to help monitor elephant activity around the water source.

Phase 7

Community Education

Launch educational activities for community members and students.

Phase 8

Monitoring & Reporting

Continue monitoring, collect project data, and prepare the final report for the community and relevant programme stakeholders.

Project roadmap

The next steps

The immediate priorities as the project moves toward construction.

Confirm Site

Meet the Village Chief and DWNP to confirm the project site.

Secure Support

Seek a co-funding commitment from a tourism partner.

Begin Pilot Construction

Target construction beginning in November.

Monitor Progress

Collect monitoring information and project updates.

Project Reporting

Report progress to the YA programme, the community and relevant stakeholders.